OUR PRESIDENT HAS SIGNED an asbestos abatement contract with Altech Environmental Inc. Next month, they will remove the original brown vinyl floor tile (and any flooring layers above it) from the Renovation Project areas: women’s restroom, men’s restroom, the twin open spaces at the back of the sanctuary, and the southeast exit corridor. They will leave an exposed subfloor in those areas.
Below the jump, this post will explain the arrangements for this crucial first step in the demolition portion of the project.…
Of the four companies that I contacted, Altech is the only one that met the following criteria: they didn’t consider our job to be too small, they were willing to cooperate on our need to move the floor safe, and they proposed taking measures whose cost and trouble are commensurate with the relatively low risk posed by our type of tile (a risk that I had discussed with our experienced Certified Asbestos Consultant).
- Their first step is to file an advance notification with the Air Quality Management District, which must be done at least 10 business days in advance.
- After removing the floor tile, they apply an encapsulant to “exposed surfaces.” The most visible portion will be like caulk along the edges of the remaining vinyl tile within the open space at the back of the sanctuary.
- They remove any baseboards—but do not replace them, which seems fine because our GC will be doing further demo work in those areas anyway.
- The work is scheduled to begin on Monday 10/5 and will take 3–4 days to complete. As the work starts, we will together mark out the exact boundaries of the abatement areas within the open space at the back of the sanctuary, using painter’s tape.
- For dealing with the tile around the floor safe, Altech has proposed the following plan. A. On Monday 10/5, they set up a containment area in the corridor, remove as much of the floor tile as they can, and clean up the area.B. On Tuesday 10/6, while they are working on the restrooms, our contractor brings a pneumatic jack and plywood, and moves the floor safe temporarily out into the sanctuary space.C. Altech returns to the corridor later that day, reestablishes the containment, and removes the remaining flooring.
- Mishkon will not be arranging for follow-up testing by an independent contractor (“third-party clearance”). It’s not required in our case, and again our Consultant considers the overall risk to be relatively low, given the type of tile involved.